Sandy Bay Airport Improvements
Federal contribution
$2.3M
$2,340,000
Federal share50%
of $4.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 27, 2022
202320242025
Built
Approved 8 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Saskatchewan Ministry of Highways and Infrastructure
- Construction start
- Jun 12, 2023(actual)
- Construction end
- Mar 31, 2025(actual)
Against the original forecast
- Construction end12 months lateforecast Mar 31, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63004 in the federal list. How to read these figures.