Five Rivers - Wastewater System Upgrades
Federal contribution
$1.3M
$1,253,514
Federal share41%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2024
202320242025
Built
Approved 2.4 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Five Rivers
- Construction start
- Aug 8, 2023(actual)
- Construction end
- Mar 12, 2025(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jul 1, 2023
- Construction end3 months lateforecast Nov 30, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63028 in the federal list. How to read these figures.