Schedule

Announced and approvedJun 30, 2022
Built

Approved 3 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Oct 29, 2022(actual)
Construction end
Nov 23, 2022(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Sep 19, 2022
  • Construction end3 weeks lateforecast Nov 4, 2022