RM of Elmsthorpe No. 100, Miller Bridge Replacement
Elmsthorpe No. 100, Saskatchewan
Federal contribution
$38,243
Federal share16%
of $245.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2022
Built
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Elmsthorpe No. 100
- Construction start
- Oct 29, 2022(actual)
- Construction end
- Nov 23, 2022(actual)
Against the original forecast
- Construction start6 weeks lateforecast Sep 19, 2022
- Construction end3 weeks lateforecast Nov 4, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63211 in the federal list. How to read these figures.