Tsuut'ina Nation Spirit Healing Lodge Restoration

Tsuu T'ina Nation, Alberta

completeOtherGICB
Federal contribution
$1.9M
$1,930,000
Federal share79%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 26, 2022
202320242025
Built

Approved 5 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
Tsuut'ina Nation
Construction start
Mar 31, 2023(actual)
Construction end
Mar 31, 2025(actual)

Against the original forecast

  • Construction start3 months earlyforecast Jul 1, 2023
  • Construction end5 months lateforecast Oct 31, 2024

Also in Tsuu T'ina Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63229 in the federal list. How to read these figures.