Schedule
Announced and approvedMar 7, 2024
20232024
Built
Approved 23 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Construction start
- Oct 10, 2022(actual)
- Construction end
- Nov 20, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 1, 2022
- Construction end6 weeks earlyforecast Dec 31, 2022