Federal contribution
$951,275
Federal share48%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2024
today
20232024202520262027
BuiltForecast

Approved 20 months before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
May 1, 2023(actual)
Construction end
Sep 30, 2027(forecast)