Lakeview Redevelopment
Federal contribution
$2.0M
$2,040,000
Federal share60%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 9, 2024
2023202420252026
Built
Approved 19 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Hudson
- Construction start
- Jun 20, 2024(actual)
- Construction end
- Dec 18, 2025(actual)
Against the original forecast
- Construction start13 months lateforecast May 31, 2023
- Construction end2.1 years lateforecast Oct 31, 2023
Also in Hudson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63445 in the federal list. How to read these figures.