Construction of a multi-use path on Road 2 East from Graham Sideroad to County Road 29

Kingsville, Ontario

completeActive TransportationATF
Federal contribution
$1.1M
$1,064,773
Federal share60%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 20, 2024
20232024
Built

Approved 20 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Town of Kingsville
Construction start
Jun 1, 2023(actual)
Construction end
Mar 4, 2024(actual)

Against the original forecast

  • Construction end3 months lateforecast Dec 4, 2023