Campus Community Connectivity at Ontario Tech University in Oshawa, ON

Durham, Ontario

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share100%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 19, 2024
20232024
Built

Approved 21 months before the announcement.

Program
Active Transportation Fund
Construction start
Jan 3, 2023(actual)
Construction end
Aug 31, 2024(actual)

Against the original forecast

  • Construction start7 months lateforecast Jun 1, 2022
  • Construction end3 months lateforecast May 31, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63524 in the federal list. How to read these figures.