Port Robinson South Main Street Bridge and Eco Park

Thorold, Ontario

completeCapacity BuildingATF
Federal contribution
$49,999
Federal share100%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 19, 2024
202220232024
Built

Approved 21 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Thorold
Construction start
Sep 22, 2021(actual)
Construction end
Nov 4, 2022(actual)

Against the original forecast

  • Construction start8 months earlyforecast Jun 1, 2022
  • Construction end3 months earlyforecast Feb 1, 2023