Yellowknives Dene First Nation Cultural Spaces Development Phase 1: Investigation, Planning and Functional Designs
Yellowknives Dene First Nation, Northwest Territories
Federal contribution
$112,500
Federal share75%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 17, 2022
today
20232024202520262027
BuiltForecast
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Yellowknives Dene First Nation
- Construction start
- Jun 2, 2026(forecast)
- Construction end
- Mar 31, 2027(forecast)
Also in Yellowknives Dene First Nation