Lazo Greenway Multi-Use Pathway for Town of Comox/Comox Valley Regional District, BC
Federal contribution
$1.0M
$1,017,930
Federal share60%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 20, 2022
2023202420252026
Built
Approved 5 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Comox Valley Regional District
- Construction start
- Jul 15, 2024(actual)
- Construction end
- Jan 31, 2026(actual)
Against the original forecast
- Construction end4 weeks lateforecast Dec 31, 2025
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63538 in the federal list. How to read these figures.