Back to projects

Linking Pathway - Memory Park to Museum to Wildlife Lands

Broadview, Saskatchewan

approvedCapacity BuildingATF
Federal contribution
$49,510
Federal share100%

of $49.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2022
2023
BuiltForecast

Approved 6 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Town of Broadview
Construction start
Sep 1, 2022(forecast)
Construction end
Mar 31, 2023(forecast)

Also in Broadview

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63547 in the federal list. How to read these figures.