Back to projects

Regional Trails System- Project A, Phase 2

Rockwood, Manitoba

completeActive TransportationATF
Federal contribution
$272,460
Federal share60%

of $454.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 19, 2023
20232024
Built

Approved 15 months before the announcement.

Program
Active Transportation Fund
Construction start
Jun 23, 2023(actual)
Construction end
Mar 26, 2024(actual)

Against the original forecast

  • Construction start12 months lateforecast Jul 4, 2022
  • Construction end2 months earlyforecast Jun 1, 2024

Also in Rockwood