Great Beech Hill Trail construction of remainder of trail
Federal contribution
$226,108
Federal share40%
of $565.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 21, 2024
202320242025
Built
Approved 21 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Sackville Lakes Park and Trails Association
- Construction start
- Sep 25, 2023(actual)
- Construction end
- Oct 31, 2025(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 30, 2023
- Construction end12 months lateforecast Oct 30, 2024
Also in Halifax