Back to projects

Construction of Walking and Cycling Paths

Grenville, Quebec

completeActive TransportationATF
Federal contribution
$502,437
Federal share60%

of $837.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2025
2023202420252026
Built

Approved 2.3 years before the announcement.

Program
Active Transportation Fund
Construction start
Aug 1, 2024(actual)
Construction end
Dec 31, 2025(actual)

Against the original forecast

  • Construction end2 months lateforecast Oct 31, 2025

Also in Grenville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63682 in the federal list. How to read these figures.