Construction for Sidewalk Extension on Principale Street

Saint-Mathieu, Quebec

completeActive TransportationATF
Federal contribution
$50,000
Federal share14%

of $347.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 5, 2025
202320242025
Built

Approved 2.4 years before the announcement.

Program
Active Transportation Fund
Construction start
Jul 3, 2023(actual)
Construction end
Nov 29, 2023(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 30, 2023
  • Construction end2 months lateforecast Sep 15, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63697 in the federal list. How to read these figures.