Herring Cove Community Centre
Federal contribution
$2.2M
$2,231,724
Federal share65%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 30, 2022
202320242025
BuiltForecast
Approved 8 weeks before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Construction start
- Mar 4, 2024(actual)
- Construction end
- Dec 31, 2024(forecast)
Against the original forecast
- Construction start2.4 years lateforecast Oct 1, 2021
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63700 in the federal list. How to read these figures.