Purchase of rolling equipment and other infrastructure necessary for the establishment of a public transit service in the Acadian Peninsula in New Brunswick
Federal contribution
$1.1M
$1,095,760
Federal share80%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2023
202320242025
Built
Approved 3 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Acadian Peninsula Regional Service Commission
- Construction start
- Jun 1, 2023(actual)
- Construction end
- Nov 15, 2025(actual)
Against the original forecast
- Construction start3 months lateforecast Mar 6, 2023
- Construction end2 weeks earlyforecast Dec 1, 2025
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63704 in the federal list. How to read these figures.