SMU Active Transportation

Halifax, Nova Scotia

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share100%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 15, 2023
20232024
Built

Approved 18 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Saint Mary's University
Construction start
May 30, 2023(actual)
Construction end
Jun 6, 2024(actual)

Against the original forecast

  • Construction start12 months lateforecast May 31, 2022
  • Construction end17 months lateforecast Dec 30, 2022