Lands End Road Multi-Use Path Survey and Concept Design

North Saanich, British Columbia

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share50%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 20, 2022
20232024
Built

Approved 6 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
District of North Saanich
Construction start
Jun 28, 2022(actual)
Construction end
Apr 30, 2024(actual)

Against the original forecast

  • Construction start4 months earlyforecast Nov 1, 2022
  • Construction end10 months lateforecast Jun 30, 2023

Also in North Saanich

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63736 in the federal list. How to read these figures.