Hartley Bay Recreation Trails

Hartley Bay, British Columbia

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share100%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2022
2023
Built

Approved 6 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Gitga'at First Nation
Construction start
Aug 1, 2022(actual)
Construction end
Mar 31, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2022
  • Construction end3 months lateforecast Dec 31, 2022

Also in Hartley Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63752 in the federal list. How to read these figures.