Town of Okotoks Active Transportation Strategy
Federal contribution
$50,000
Federal share67%
of $75.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 26, 2024
20232024
Built
Approved 2 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Okotoks
- Construction start
- Jul 20, 2023(actual)
- Construction end
- Nov 25, 2024(actual)
Against the original forecast
- Construction start14 months lateforecast May 16, 2022
- Construction end12 months lateforecast Nov 30, 2023