Truro Amateur Athletic Club Multi-use Sport Facility Revitalization and Relocation of Senior Baseball Facility
Federal contribution
$3.2M
$3,200,000
Federal share34%
of $9.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 12, 2022
2023202420252026
Built
Approved 8 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Truro
- Construction start
- Aug 21, 2023(actual)
- Construction end
- Dec 22, 2025(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 7, 2023
- Construction end5 months earlyforecast Jun 2, 2026
Also in Truro