Kimberley Paved Pathway Network Extension, Province of BC

Kimberley, British Columbia

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share89%

of $56.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2022
20232024
Built

Approved 6 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Kimberley Trails Society
Construction start
Aug 7, 2022(actual)
Construction end
Mar 31, 2024(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 4, 2022
  • Construction end3 months lateforecast Dec 31, 2023

Also in Kimberley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63802 in the federal list. How to read these figures.