Kimberley Paved Pathway Network Extension, Province of BC
Federal contribution
$50,000
Federal share89%
of $56.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 19, 2022
20232024
Built
Approved 6 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Kimberley Trails Society
- Construction start
- Aug 7, 2022(actual)
- Construction end
- Mar 31, 2024(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jul 4, 2022
- Construction end3 months lateforecast Dec 31, 2023
Also in Kimberley