Back to projects

Resort Village of Saskatchewan Beach - Upgrade Sailing Clubhouse

Resort Village of Saskatchewan Beach, Saskatchewan

completeRecreationRNIS
Federal contribution
$46,043
Federal share40%

of $115.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 6, 2022
202320242025
Built

Approved 3 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
May 21, 2024(actual)
Construction end
Mar 31, 2025(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 1, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63872 in the federal list. How to read these figures.