Purchase of vehicles for pre-booked, door-to-door, wheelchair accessible service for the residents in Shelburne County (Nova Scotia)
Federal contribution
$453,915
Federal share80%
of $567.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 12, 2024
2023202420252026
BuiltForecast
Approved 2.2 years before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Sou'West Nova Transit Association
- Construction start
- Jan 26, 2023(actual)
- Construction end
- Mar 31, 2026(forecast)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63878 in the federal list. How to read these figures.