Purchase of accessible vehicles to support the transportation service in western Kings County and Annapolis County, Nova Scotia

Annapolis, Nova Scotia

completePublic TransitRTSF
Federal contribution
$222,010
Federal share80%

of $277.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 1, 2024
202320242025
Built

Approved 24 months before the announcement.

Program
Permanent Public Transit Program
Construction start
Feb 16, 2023(actual)
Construction end
Jan 22, 2025(actual)

Against the original forecast

  • Construction start6 months lateforecast Sep 1, 2022
  • Construction end5 months lateforecast Aug 30, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63879 in the federal list. How to read these figures.