Purchase of two vehicles for on-demand, door-to-door service in Rural Municipality of Piney and the Buffalo Point First Nation (Manitoba).

Buffalo Point First Nation, Manitoba

completePublic TransitRTSF
Federal contribution
$153,700
Federal share70%

of $218.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 27, 2024
202320242025
Built

Approved 21 months before the announcement.

Program
Permanent Public Transit Program
Ultimate recipient
Rural Municipality of Piney
Construction start
Jul 1, 2023(actual)
Construction end
Mar 14, 2025(actual)

Against the original forecast

  • Construction start6 months lateforecast Jan 10, 2023
  • Construction end8 months lateforecast Jun 30, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63895 in the federal list. How to read these figures.