Rural Municipality (RM) of Mount Pleasant No.2 - North Bridge Replacement
Mount Pleasant No. 2, Saskatchewan
Federal contribution
$166,700
Federal share17%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 14, 2022
2023
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- RM of Mount Pleasant No. 2
- Construction start
- Sep 5, 2023(actual)
- Construction end
- Nov 9, 2023(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2023
Also in Mount Pleasant No. 2
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63899 in the federal list. How to read these figures.