Schedule

Announced and approvedOct 6, 2022
202320242025
Built

Approved 3 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Apr 1, 2024(actual)
Construction end
Sep 30, 2025(actual)

Against the original forecast

  • Construction start6 months lateforecast Oct 1, 2023
  • Construction end4 months lateforecast May 31, 2025