Federal contribution
$4.4M
$4,371,287
Federal share75%
of $5.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 6, 2022
202320242025
Built
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Mosquito, Grizzly Bear's Head, Lean Man First Nation
- Construction start
- Apr 1, 2024(actual)
- Construction end
- Sep 30, 2025(actual)
Against the original forecast
- Construction start6 months lateforecast Oct 1, 2023
- Construction end4 months lateforecast May 31, 2025