Back to projects

Purchase of vehicles to expand a rural transit solution that operates in Guysborough County, Town of Mulgrave and surrounding areas, Nova Scotia

Guysborough, Nova Scotia

completePublic TransitRTSF
Federal contribution
$125,702
Federal share80%

of $157.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 27, 2023
20232024
Built

Approved 8 months before the announcement.

Program
Permanent Public Transit Program
Construction start
Apr 1, 2023(actual)
Construction end
Jan 29, 2024(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 1, 2022
  • Construction end3 months lateforecast Nov 1, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63905 in the federal list. How to read these figures.