RM of Hudson Bay No. 394, Twp 454A, Rg 2042 Bridge Replacement
Hudson Bay No. 394, Saskatchewan
Federal contribution
$131,669
Federal share17%
of $789.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 18, 2023
202320242025
Built
Approved 6 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- RM of Hudson Bay No. 394
- Construction start
- Oct 21, 2024(actual)
- Construction end
- Dec 9, 2024(actual)
Against the original forecast
- Construction end4 months earlyforecast Mar 31, 2025
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63910 in the federal list. How to read these figures.