Rural Municipality of Miry Creek No. 229, Green Bridge Replacement

Miry Creek No. 229, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$134,194
Federal share17%

of $805.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 14, 2022
20232024
Built

Approved 5 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
RM of Miry Creek No. 229
Construction start
Oct 21, 2024(actual)
Construction end
Nov 27, 2024(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Sep 1, 2024
  • Construction end4 weeks lateforecast Oct 31, 2024

Also in Miry Creek No. 229

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63913 in the federal list. How to read these figures.