Back to projects

RM of Laurier No. 38, Martin Bridge Replacement

Laurier No. 38, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$166,700
Federal share17%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 25, 2023
20232024
Built

Approved 4 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jul 4, 2024(actual)
Construction end
Oct 21, 2024(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 1, 2024
  • Construction end7 weeks lateforecast Aug 31, 2024

Also in Laurier No. 38