RM of Laurier No. 38, Martin Bridge Replacement
Federal contribution
$166,700
Federal share17%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 25, 2023
20232024
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Laurier No. 38
- Construction start
- Jul 4, 2024(actual)
- Construction end
- Oct 21, 2024(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jun 1, 2024
- Construction end7 weeks lateforecast Aug 31, 2024
Also in Laurier No. 38