Purchase of Vehicles for On-Demand and Accessible Transportation Services in Southeast New Brunswick
Federal contribution
$1.1M
$1,082,801
Federal share80%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 13, 2025
today
202320242025202620272028
BuiltForecast
Approved 2.4 years before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Southeast Regional Service Commission
- Construction start
- Oct 22, 2022(actual)
- Construction end
- Dec 31, 2027(forecast)
Against the original forecast
- Construction start2 months earlyforecast Jan 1, 2023
Also in Albert County
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63920 in the federal list. How to read these figures.