Wawanesa and District Recreation Centre Retrofit

Oakland-Wawanesa, Manitoba

completeRecreationGICB
Federal contribution
$832,169
Federal share80%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 9, 2023
20232024
Built

Approved 9 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Feb 9, 2022(actual)
Construction end
Dec 20, 2023(actual)

Against the original forecast

  • Construction start4 months earlyforecast Jun 1, 2022
  • Construction end12 months lateforecast Dec 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63924 in the federal list. How to read these figures.