Eden Valley Arena Energy Retrofit
Bearspaw First Nation, Eden Vally, Alberta
Federal contribution
$1.5M
$1,453,632
Federal share100%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 16, 2024
2023202420252026
BuiltForecast
Approved 20 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Bearspaw First Nation No. 473
- Construction start
- Jun 20, 2023(actual)
- Construction end
- Mar 31, 2026(forecast)
Against the original forecast
- Construction start3 months lateforecast Apr 1, 2023