Purchase of a vehicle to provide on-demand transportation service in Fort Simpson, Northwest Territories

Fort Providence, Northwest Territories

completePublic TransitRTSF
Federal contribution
$85,000
Federal share89%

of $95.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 6, 2025
202320242025
Built

Approved 2.3 years before the announcement.

Program
Permanent Public Transit Program
Ultimate recipient
Liidlii Kue First Nation
Construction start
Sep 30, 2023(actual)
Construction end
Mar 20, 2025(actual)

Against the original forecast

  • Construction start16 months lateforecast Jun 1, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63936 in the federal list. How to read these figures.