Purchase of vehicles to provide transportation services to the residents of Sipekne'katik, Nova Scotia.
Federal contribution
$450,682
Federal share100%
of $450.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2026
2023202420252026
Built
Approved 3.5 years before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Sipekne'katik First Nation
- Construction start
- Jan 17, 2023(actual)
- Construction end
- Dec 5, 2025(actual)
Against the original forecast
- Construction end5 months lateforecast Jun 24, 2025
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63939 in the federal list. How to read these figures.