Retrofitting Wakas Hall
Tsulquate Reserve, Port Hardy, British Columbia
Federal contribution
$2.4M
$2,354,773
Federal share98%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 12, 2024
2023202420252026
Built
Approved 23 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Gwa'sala-'Nakwaxda'xw Nation
- Construction start
- Jun 11, 2024(actual)
- Construction end
- Jan 31, 2026(actual)
Against the original forecast
- Construction start8 weeks lateforecast Apr 15, 2024
- Construction end5 months earlyforecast Jun 26, 2026
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63940 in the federal list. How to read these figures.