Retrofitting Wakas Hall

Tsulquate Reserve, Port Hardy, British Columbia

completeOtherGICB
Federal contribution
$2.4M
$2,354,773
Federal share98%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 12, 2024
2023202420252026
Built

Approved 23 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Jun 11, 2024(actual)
Construction end
Jan 31, 2026(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Apr 15, 2024
  • Construction end5 months earlyforecast Jun 26, 2026

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63940 in the federal list. How to read these figures.