Back to projects

Purchase of vehicles and supporting infrastructure to support transit serving Kapawe'no First Nation, Grouard, Driftpile First Nation, Sucker Creek First Nation, Sawridge First Nation in Alberta

Big Lakes, Alberta

completePublic TransitRTSF
Federal contribution
$3.8M
$3,816,894
Federal share99%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 26, 2024
202320242025
Built

Approved 17 months before the announcement.

Program
Permanent Public Transit Program
Ultimate recipient
Kapawe'no First Nation
Construction start
Jul 1, 2023(actual)
Construction end
Jun 30, 2025(actual)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63964 in the federal list. How to read these figures.