Purchase of vehicles and supporting infrastructure to support transit serving Kapawe'no First Nation, Grouard, Driftpile First Nation, Sucker Creek First Nation, Sawridge First Nation in Alberta
Federal contribution
$3.8M
$3,816,894
Federal share99%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 26, 2024
202320242025
Built
Approved 17 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Kapawe'no First Nation
- Construction start
- Jul 1, 2023(actual)
- Construction end
- Jun 30, 2025(actual)