Purchase of an accessible vehicle to provide transit service for the Kispiox community members in the Bulkley/Skeena catchment area, British Columbia
Federal contribution
$116,811
Federal share100%
of $116.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 9, 2026
2023202420252026
Built
Approved 3.2 years before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Kispiox Band Council
- Construction start
- Sep 30, 2023(actual)
- Construction end
- Jul 11, 2025(actual)
Against the original forecast
- Construction start16 months lateforecast Jun 1, 2022
- Construction end15 months lateforecast Mar 31, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63969 in the federal list. How to read these figures.