Purchase of a vehicle to support demand-response transit system in the County of Two Hills, Alberta
Federal contribution
$80,000
Federal share67%
of $120.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 26, 2024
202320242025
Built
Approved 17 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Two Hills Family and Community Services Society
- Construction start
- Apr 1, 2023(actual)
- Construction end
- Feb 26, 2025(actual)
Against the original forecast
- Construction start11 months lateforecast May 1, 2022
- Construction end23 months lateforecast Mar 31, 2023