Purchase of an accessible vehicle to provide transit service for the Municipality of Ste-Rose du Lac and Rural Municipality of Lakeshore, Manitoba
Federal contribution
$76,800
Federal share68%
of $112.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 28, 2023
20232024
Built
Approved 12 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Ste. Rose and District Handivan
- Construction start
- Sep 30, 2023(actual)
- Construction end
- Sep 11, 2024(actual)
Against the original forecast
- Construction end13 months earlyforecast Sep 30, 2025