Back to projects

RÉGÎM: electrification of the fleet to improve quality of the service while reducing GES emission – Gaspésie - Îles-de-la-Madeleine (Quebec)

Bonaventure, Quebec

underwayPublic TransitRTSF
Federal contribution
$5.0M
$5,000,000
Federal share73%

of $6.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 17, 2024
today
202320242025202620272028
BuiltForecast

Approved 21 months before the announcement.

Program
Permanent Public Transit Program
Construction start
Jan 1, 2024(actual)
Construction end
Mar 31, 2028(forecast)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63990 in the federal list. How to read these figures.