Purchase of vehicles for pre-booked, on-demand service in Kentville, Wolfville, and Berwick and the Incorporated Villages of New Minas, Canning, and Port Williams (Nova Scotia)
Federal contribution
$302,562
Federal share80%
of $378.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 23, 2023
2023202420252026
Built
Approved 4 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Kings Point to Point Transit Society
- Construction start
- Sep 1, 2023(actual)
- Construction end
- Mar 4, 2026(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Mar 31, 2026
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63999 in the federal list. How to read these figures.