Purchase of vehicles and supporting infrastructure to provide transit service in the Bow Valley, Alberta
Federal contribution
$3.9M
$3,899,554
Federal share80%
of $4.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 26, 2024
2023202420252026
Built
Approved 19 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Bow Valley Regional Transit Services Commission
- Construction start
- Aug 22, 2023(actual)
- Construction end
- May 15, 2026(actual)
Against the original forecast
- Construction start10 months lateforecast Oct 31, 2022
- Construction end6 weeks lateforecast Mar 31, 2026
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64007 in the federal list. How to read these figures.