Schedule

Announced and approvedMay 15, 2024
20232024
Built

Approved 16 months before the announcement.

Program
Permanent Public Transit Program
Ultimate recipient
Senior Wheels Association
Construction start
Aug 1, 2023(actual)
Construction end
May 5, 2024(actual)

Against the original forecast

  • Construction start10 months lateforecast Oct 1, 2022
  • Construction end5 weeks lateforecast Mar 31, 2024