Purchase of an accessible diesel vehicle and supporting infrastructure to provide transit service for the George Gordon First Nation, Saskatchewan
Federal contribution
$1.3M
$1,322,500
Federal share100%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 10, 2024
202320242025
BuiltForecast
Approved 16 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- George Gordon First Nation
- Construction start
- Apr 1, 2024(actual)
- Construction end
- Mar 31, 2025(forecast)
Against the original forecast
- Construction start15 months lateforecast Jan 2, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64011 in the federal list. How to read these figures.