Purchase of an accessible diesel vehicle and supporting infrastructure to provide transit service for the George Gordon First Nation, Saskatchewan

Punnichy, Saskatchewan

underwayPublic TransitRTSF
Federal contribution
$1.3M
$1,322,500
Federal share100%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 10, 2024
202320242025
BuiltForecast

Approved 16 months before the announcement.

Program
Permanent Public Transit Program
Ultimate recipient
George Gordon First Nation
Construction start
Apr 1, 2024(actual)
Construction end
Mar 31, 2025(forecast)

Against the original forecast

  • Construction start15 months lateforecast Jan 2, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64011 in the federal list. How to read these figures.